Project Indie — Renovation Schedule

Project Indie — Renovation schedule

30, rue de l'Indépendance, Strassen  ·  12 October – mid-December 2026

Eduardo — construction
Kitchen — Vincent
Blackwood — joinery
Garden / terrace
Materials to order
⚠
One question for you: During the main works (12 Oct – 27 Nov), we propose setting up a temporary kitchen in the basement so the family can continue living at home comfortably. Does this work for you?

Actions required now

📞Claudia and Mike — please contact Vincent to confirm the kitchen order and secure a delivery date. This is the last piece needed to lock the full schedule.Urgent
🛒Tiles, cornices, and paint must be ordered and on site by 1 November — Eduardo will need them for the second half of his works.Order now
📄Eduardo to provide a quote for the terrace / garden works.Pending quote
✅Eduardo construction start confirmed — 12 October 2026.Confirmed